Project Description

Due to an ongoing drainage issue, the Lewis Street Storm Water Improvements project will construct a swale in the rear of the properties located at 803, 809, and 811 Lewis Street. An area inlet will be installed, roughly 13’ of 24” reinforced concrete pipe, and a storm manhole close to and on Eighth Street. There are miscellaneous removals and repair of sidewalk, retaining wall and fencing.

Project Location

Southwest corner of Lewis Street and Eighth Street.
PROJECT MAP

Contact Information

Todd Strong
Construction - Project Manager
636-949-3594
Todd.Strong@stcharlescitymo.gov 

Project Activities

  • Tree clearing and miscellaneous removals. Project began in November 2021.
  • Sod needs to be laid still and special-ordered fence fates should be delivered by the end of April 2022. 
Lewis St two prejob