This project will address failing roadway pavement via full depth reconstruction of the roadway on West Clay Street. Additionally, sidewalk infrastructure will be constructed on each side of West Clay Street where existing sidewalk is non-compliant with ADA accessibility standards and/or locations where sidewalks do not currently exist.
Project Location
Along the intersections of White Gate Lane to Duchesne Drive and Hawks Nest Drive. Project Map (PDF)
Contact Information
Coralie Steuber Project Manager 636-949-3237
Current Project Activities
In May of 2017, the contractor completed the pavement markings at Westbury and Kingston Terrace
In November of 2016, the contractor broke and removed new pavement sections that did not meet strength requirements
Westbury (at the Ford dealership) was reopened to traffic in mid-July
New pavement was opened to traffic in late July
The westbound lanes are closed so crews can rebuild the lanes
Forms were set on the westbound lanes during the first week of August
Main line paving of the Westbound lanes was complete in August
Utility relocation agreements are complete
Temporary striping is complete. There is no left turn from West Clay driving eastbound onto Duchesne and the double yellow line throughout the project limits means two way traffic - one lane each direction
The contractor has completed the installation of the new 12" water main in the Eastbound lanes of West Clay
Contractors tested for utility conflicts so that storm sewer improvements could move forward
Construction of the retaining wall on the south-side of West Clay is complete
Milling and pavement removal began the week of 4/18/2016