Droste Road Reconstruction - 15STR25

Construction Ward - 9

Impacted Wards - Citywide

Project Description


This project encompasses the roadway reconstruction of Droste Road from West Clay Street to Duchesne Drive. The improvements will include complete pavement reconstruction, sidewalk improvements, utility adjustments & driveway access improvements.

Project Location


Along Droste Road from West Clay Street to Duchesne Drive.
Project Map

Contact Information


Matt Seggerman
Project Manager
636-949-3237

Current Project Activities

 
  • Field survey and submittal was completed in July 2016
  • Right-of-Way acquisition was completed in August 2016
  • Plan, Specification and estimate (PS&E) approval was completed in October 2016 
  • Design for this project is 91% complete
  • Construction is scheduled to begin in early spring 2017

Public Meeting #2 

  • A second public meeting was held on Thursday, January 7, 2016 regarding the reconstruction of Droste Road between Charbo Street and South Duchesne Drive 
  • At the meeting, large exhibit boards of the project, including right-of-way and easement impacts to properties, were on display for the public to see. Also, a handout was available that discusses the details of the project including: a start date for construction, construction timeline, and traffic impacts to local residents and business owners. 

 

Project Timeline

droste timeline

Project Progress

droste progress

Project Budget

droste budget

This project made possible through Gaming funds.