Convention Center Blvd. Extension - 17STR32

Construction Ward - 3

Project Description

The Convention Center Blvd. (S. Fairgrounds Road) Extension Project will connect two dead end sections, replace the driving surface and provide direct access to I-70 at the Convention Center Blvd. interchange.
  


Project Location

Convention Center Blvd from Sherbrooke Rd. to the Saint Charles Convention Center.

Contact Information


Nicholas Galla
Project Manager
636-949-3237

Current Project Activities


  • The City is currently in the design stage of the project
  • Property surveying began in late January 2017
  • On May 17, 2017 the County Road Board approved the roadway alignment 
  • A second Open House occurred on May 18, 2016. Public Works staff were on hand and discussed the project with area residents
  • A third Open House was held on November 6, 2017 at the Saint Charles Convention Center in room 103
  • Crews began the demolition of 1816 Fairgrounds the week of October 14, 2018

Project Timeline

convention timeline

Project Progress

convention progress

Project Budget

convention budget