Convention Center Boulevard Extension - 17STR32

Construction Ward - 3

Project Description

The Convention Center Boulevard (South Fairgrounds Road) Extension Project will connect two dead end sections, replace the driving surface and provide direct access to Interstate 70 at the Convention Center Boulevard interchange.

Project Location

Convention Center Boulevard from Sherbrooke Road to the Saint Charles Convention Center.

Contact Information

Jon Swagman
Project Manager
636-949-3237

Current Project Activities

  • The City is currently in the design stage of the project
  • Property surveying began in late January 2017
  • On May 17, 2017 the County Road Board approved the roadway alignment
  • A second Open House occurred on May 18, 2016. Public Works staff were on hand and discussed the project with area residents
  • A third Open House was held on November 6, 2017 at the Saint Charles Convention Center in room 103
  • Crews completed the demolition of 1816 Fairgrounds in October 2018

Project Timeline

convention center timeline

Project Progress

convention center progress

Project Budget

convention budget