Project Description
To accommodate a growing population, the City of St. Charles has designed and is in the process of constructing a new water well which will increase raw water supply to Elm Point Water Treatment Plant by two million gallons per day.
Project Location
3740 Huster Road
Project Map (PDF)
Contact Information
Dave Bauman
Assistant Project Manager
Construction Inspector
(636) 949-3237
Current Project Activities
- The City has completed design plans and specifications a for the new water well
- Bids were opened March 2, 2016
- Construction of the well began in April 2016
- The contractor has finished drilling the well and has installed a new 12” raw water line and valve vault
- The contractor is constructing the platform