West Clay Rehabilitation - East - 15STR33

Construction Ward - 9
Contractor - Krupp Construction

This project will overhaul West Clay Street from Duchesne to west of First Capitol Drive. The project will also realign the intersection of Droste and West Clay and remove a redundant signal at Chargene. The existing pavement in this corridor is in poor condition. The sidewalks are disconnected and in poor repair. The overhead utilities make improvements along the route difficult to construct. The project will rehab the roadway, provide bicycle and pedestrian facilities along West Clay Street, underground the overhead utilities, install decorative lighting and improve roadway drainage. The project has received outside funding from the County Road Board and the project was recommended in the Droste West Clay Duchesne Study to assist in the revitalization of the area.

Project Location

West Clay Street from Duchesne to west of First Capitol Drive

Contact Information

Coralie Steuber
Project Manager
636-949-3237

Current Project Activities

  • County Road Board Funds were awarded in 2015
  • Federal STP-S funding application was submitted on March 3, 2016, and requested $1 million in federal funds
  • Design Notice to proceed and Kick-off Meeting were held on April 12, 2016
  • Open House was held on November 2, 2016
  • AT&T Traffic Plan (PDF)
  • Contractors will be demolishing 4 properties as a part of this project:
    • 501 Droste Road
    • 2408 West Clay Street
    • 2407 West Clay Street
    • 1010 Chargene Street
  • Spire began working on their West Clay utility relocations in August 2018
  • On Monday, April 8, the contractor will remove the signal lights at the intersection of Chargene and West Clay
  • On Tuesday, April 9, traffic between Droste and Duchesne will be moved to the northside of West Clay. All businesses will be accessible

Related Documents

Progress Timeline

west clay timeline

Progress Graph

west clay progress

Project Budget

west clay budget

Project Risks

west clay east risks