Cole Creek Flood Reduction Project - Elm Point ROAD to Runnymede DRIVE - 16STM8

Construction Ward - 10
Contract Awarded to: Ideal Landscape Group

Project Description

This project will include creek channel widening and creek bank improvements along Cole Creek to reduce the risk of flooding in the area. Design of the project has been contracted to M3 Engineering Group. The design is anticipated to be complete in December 2018 with construction beginning in Spring 2019.

Project Location

Cole Creek from Norfolk Southern railway bridge (Elm Point Road) to Runnymede Drive bridge.

Contact Information

David Bauman
Project Manager
636-949-3237


Current Project Activities

  • A project Open House was held on October 11, 2018
  • Design completed in December 2018
  • Construction is anticipated to begin in Spring 2019
  • Crews began moving equipment on site the week of February 18, 2019
  • Clearing began the week of February 24 
  • Runnymede Drive closed at Cole Creek on April 4, 2019
  • Construction of the modular wall started the week of March 31

Related Documents 


Project Timeline

runnymede timeline

Project Progress

runnymede progress

Project Budget

cole creek budget