Cole Creek Flood Reduction Project - Elm Point Road to Runnymede Drive

Impacted Ward: 10
Contractor: Ideal Landscape Group

Project Description

This project will include creek channel widening and creek bank improvements along Cole Creek to reduce the risk of flooding in the area. Design of the project has been contracted to M3 Engineering Group. 

Project Location

Cole Creek from Norfolk Southern railway bridge (Elm Point Road) to Runnymede Drive bridge.
Project Map

Contact Information

David Bauman
Project Manager
636-949-3236
david.bauman@stcharlescitymo.gov 

Current Project Activities

  • A project Open House was held on October 11, 2018
  • Design completed in December 2018
  • Construction began in Spring 2019
  • Replacing roadway pavement on Elm Street began the week of February 24, 2020.
  • All lanes are now open to traffic. Ideal Landscape completed pavement, final grading, and placing seed and straw
  • Project estimated to be complete by the end of March 2020.

Related Documents