Watson Street 12FF - Improve Fire Flow - 16WTR23

Construction Ward - 9
Contractor - Bates Utility Company, Inc.

Project Description

 
This project will improve flow in the area along Watson St., making connection to a 16” main which lies south of Lindenwood Dr. and north of the Lindenwood University campus stadium.  This project was identified as a high priority fire flow improvement in the 2011 Water Master Plan.  

Project Location


Watson Street, South of Lindenwood Dr. & North of Lindenwood University Stadium

Contact Information


Coralie Stueber
Project Manager
636-949-3237


Current Project Activities

 
  • Preliminary Plan design completed in August 2016
  • Survey notices were issued in May 2016
  • Project charter was approved in January 2016
  • Preconstruction meeting was held on June 19, 2017
  • Bates Utility Company placed no parking signs and began potholing for utilities in late June
  • Construction began the week of June 25, 2017
    • The week of July 16, crews completed the connection of a new 12 inch main to the existing 16 inch main near the Lindenwood Student Athlete Center
    • Crews made two water main tap connections on Kingshighway the week of July 23 
    • The week of August 6, crews laid new water main up Watson to Anderson St. 
    • The week of August 20, crews have installed the new main up to Gamble

Project Timeline

watson timeline

Project Progress

watson progress

Project Budget

watson budget