Project Activities

  • Project Charter approved in July 2016
  • Right of Way acquired in October 2017
  • Design was completed in May 2018
  • Bidding was completed May 2018
  • Construction began in September 2018
  • Conflict with Ameren utilities was identified in September 2018
  • Crews poured the concrete entrance for Craftsman the week of October 28, 2018
  • Crews navigated the Ameren utility conflict the week of November 18, 2018
  • Crews crossed Elm Point Industrial Drive the week of November 25, 2018