Boschert Creek Lower Trunkmain - 16SWR21

Construction Ward - 8
Contractor - Unnerstall 

Project Description

 

This project will improve the sanitary sewer capacity along the Boschert Creek trunkmain near Mueller Road, south across MO 370.  The Mississippi trunkmain model identified this area needed additional capacity during wet weather conditions. 
 

Project Location

 
Near Mueller Rd and MO 370

Contact Information


Dave Bauman
Project Manager
636-949-3237

Current

Project Activities

  • Project Charter approved in July 2016
  • Right of Way acquired in October 2017
  • Design was completed in May 2018
  • Bidding was completed May 2018
  • Construction began in September 2018

Project Timeline

boschert timeline

Project Progress

boschert progress

Project Budget

boschert creek budget