Construction Ward - 8
Contractor - Unnerstall
Project Description This project will improve the sanitary sewer capacity along the Boschert Creek trunkmain near Mueller Road, south across Missouri Highway 370. The Mississippi trunkmain model identified this area needed additional capacity during wet weather conditions.
Project Location
Near Mueller Rd and Missouri Highway 370
Contact Information
Dave Bauman
Project Manager
636-949-3237
Current Project Activities
- Project Charter approved in July 2016
- Right of Way acquired in October 2017
- Design was completed in May 2018
- Bidding was completed May 2018
- Construction began in September 2018
- Crews identified an AT&T utility conflict the week of September 30
- Poured new entrance for Craftsman the week of October 28, 2018
- Utility conflict circumvented the week of November 11, 2018
- Watermain relocation complete the week of December 16, 2018