Boschert Creek Lower Trunkmain - 16SWR21

Construction Ward - 8
Contractor - Unnerstall

Project Description This project will improve the sanitary sewer capacity along the Boschert Creek trunkmain near Mueller Road, south across Missouri Highway 370. The Mississippi trunkmain model identified this area needed additional capacity during wet weather conditions.

Project Location

Near Mueller Rd and Missouri Highway 370

Contact Information

Dave Bauman
Project Manager
636-949-3237

Current Project Activities

  • Project Charter approved in July 2016
  • Right of Way acquired in October 2017
  • Design was completed in May 2018
  • Bidding was completed May 2018
  • Construction began in September 2018
  • Crews identified an AT&T utility conflict the week of September 30
  • Poured new entrance for Craftsman the week of October 28, 2018
  • Utility conflict circumvented the week of November 11, 2018
  • Watermain relocation complete the week of December 16, 2018

Project Timeline

boschert timeline

Project Progress

boschert progress

Project Budget

boschert budget