Construction Ward - 7
Project Description
The area immediately upstream of this project has been experiencing sanitary sewer backups during storm events. In 2014 and 2015 City Staff modeled and inspected the sewer mains in this area. It was determined that the sanitary backups in the area could be eliminated by upgrading the existing 8 inch sewer to a 12 inch sewer for approximately 250 feet.
Contact Information
Marty Aubuchon
Project Manager
636-949-3237
Current
Project Activities
- Project Charter approved in January 2016
- Survey was approved in March 2016
- Preliminary Plans were submitted on August 1, 2016
- Construction will begin as early as November 1, 2017
- The week of October 30, 2017, the contractor will close West Adams between Boschert Dr & St. Leonard Ct. This closure will remain in place throughout construction