Cole Creek Bank Stabilization Project at Zumbehl

Project Description


Cole Creek is actively widening and its west bank is at risk of encroaching onto adjacent buildings and a parking lot. In order to control the current erosion, the conceptual solution is to stabilize the east and west side banks.

Project Location


The project site is located in Cole Creek from the Zumbehl Road Culverts upstream approximately 560 feet.

Contact Information


Mark Rees
Project Manager 
636-949-3237

Current Project Activities


  • Project charter was approved in October 2016
  • Design is scheduled to be complete in Spring 2018
  • Right-of-Way is scheduled to be complete in Spring 2018
  • Construction is scheduled to begin in Spring 2018 and be substantially complete by early 2019



Project Timeline

cole timeline

Project Progress

cole progress