Cole Creek Bank Stabilization Project at Zumbehl - 17STM18

Construction Ward - 6
Contract awarded to: KCI Construction

Project Description


Cole Creek is actively widening and its west bank is at risk of encroaching onto adjacent buildings and a parking lot. In order to control the current erosion, the solution is to stabilize the east and west side banks.

Project Location


The project site is located in Cole Creek from the Zumbehl Road Culverts upstream approximately 560 feet.

Contact Information


Alex Linneman
Project Manager 
636-949-3237

Current Project Activities


  • Project charter was approved in October 2016
  • Design is scheduled to be complete in Spring 2018
  • Right-of-Way is scheduled to be complete in Spring 2018
  • Construction is scheduled to begin in Spring 2018 and be substantially complete by early 2019
  • Winning bidder is KCI Construction Company
  • Week of August 12, crews began removing overgrowth and grading the creek bank
  • A temporary construction access road was rocked the week of August 19
  • The week of August 26, crews began removing dirt of the south slope

Related Documents





Project Timeline

cole zumbehl timeline

Project Progress

cole zumbehl progress

Project Budget

cole zumbehl budget