Truman Road Reconstruction Phase I - 17STR12

Construction Ward - 6
Contractor - Millstone Weber, LLC

Project Description   


Truman Road Reconstruction Project will replace the pavement along Truman Road from West Clay Street to the Southern Approach Slab for the Railroad Bridge (north of Ehlmann Rd.).  This project has been split into 2 phases.  Truman Road Reconstruction Phase 1 is from West Clay Street to Point West Blvd.  The project includes a new 5’ wide sidewalk along the south side of the roadway and a new 10’ shared use path to accommodate bicycle traffic along the north side.  Phase 1 includes raising Truman Road at West Clay Street to improve the sight distance at the intersection.  The project improves safety, ADA pedestrian and bicycle accessibility, and replaces pavement in poor condition.

Project Location
Truman Road from Point West Blvd. to South Approach Slab for RR Bridge.

Contact Information



Senior Project Manager 
636-949-3237


Current Project Activities
  • Design Kick-off meeting was held in early January 2017
  • Phase 1 construction to begin in Summer 2017
  • Preconstruction meeting was held on June 7, 2017
  • Construction will begin the week of June 26, 2017

Additional Documents


Truman Road Reconstruction Phases


Project Timeline

truman ph 1 timeline

Project Progress

truman ph 1 progress

Project Budget

truman budget