Prongue Dr Relocation Project

Construction Ward - 5

Project Description

The intersection of Bogey Estates Dr and Muegge Rd which is north of the Prongue Dr is unsignalized with Bogey Estates Dr stopping at Muegge Rd. During the AM and PM rush hours, drivers exiting and entering out and in of Bogey Estates Dr onto Muegge Rd have a difficult time finding adequate gaps in traffic. The project will relocate Prongue Dr (Wapelhorst Park Entrance) across from Bogey Estates Dr on Muegge Rd. The intersection of the relocated Prongue Dr/Bogey Estates Dr and Muegge Rd will be signalized with pedestrian crossings. The relocated Prongue Dr will have two 15’ driving lanes divided by a lighted landscaped median strip. A 10’ shared use path will be constructed parallel to Prongue Dr on the south side. A commercial entrance will be constructed connecting Prongue Dr and the existing Park’s maintenance facility. All work will occur on City and Park ROW with possibly Utility and Construction Easements.

Project Location

The intersection of Bogey Estates Dr and Muegge Rd

Contact Information

Engineering Project Manager - Traffic
Matt Seggerman
636-949-3237

Parks Department Project Manager
Chris Atkinson
636-949-3372

Current Project Activities

  • Consultant Solicitation completed in March 2017
  • Design Notice to Proceed issued in May 2017
  • Concept Plan completed in June 2017
  • Public Meetings held in September 2017
  • On September 5, 2017 City Council did not approve this solution. The Department of Engineering will continue to evaluate safety solutions for this intersection