Truman Road Reconstruction, Phase 2

Construction Ward - 6

Project Description

This project was been split into 2 phases.  Truman Road Reconstruction Phase 1 was from West Clay Street to Point West Boulevard Phase 2 is from Point West Boulevard to Ehlmann Road. This project will improve safety, Americans with Disabilities Act (ADA) pedestrian and bicycle accessibility. The project will also replace pavement in poor condition. 

Contact Information

Dave Bauman
Project Manager
636-949-3237

Current Project Activities

  • Millstone Weber started to remove the existing pavement the week of March 25
  • The Sunbrook Apartment entrance was poured the week of April 16
  • The approach to Chemtron was complete the week of May 6
  • Crews will begin paving operations on the northbound lanes of Truman the week of June 10
  • The week of July 22, Millstone Weber worked on entrances at Phillips 66, the Surgery Center and No Leash Dog Grooming. Crews also worked on back stabilization at the creek crossing as well as excavating the existing southbound lanes
  • The week of August 12, Millstone Weber continued excavating the southbound lanes and placing rock base for the road. Crews also worked on stormwater improvements on the westside of Truman and began grading and placing rock base for the 10 foot multi-use path
  • Stormwater collection upgrades were complete the week of August 26, 2018
  • The week of September 23, crews placed the base layers of asphalt for the southbound lanes
  • The southbound lane pavement was completed the week of September 30. These lanes will remain closed until the new multi-use path work is done
  • Southbound lanes were striped the week of October 21. one lane has been opened to traffic. The other southbound lane will remain closed until the multi-use path is complete
  • Guardrail installation was complete the week of October 21
  • Project was substantially complete the week of December 9, 2018
  • All lanes reopened to traffic on December 13, 2018

Project Timeline

truman timeline

Project Progress

truman progress

Project Budget

truman budget