Truman Road Reconstruction, Phase 2

Construction Ward - 6

Project Description

This project was been split into 2 phases.  Truman Road Reconstruction Phase 1 was from West Clay Street to Point West Blvd. Phase 2 is from Point West Blvd. to the south approach slab for the railroad bridge. This project will improve safety, ADA pedestrain and bicycle accessibility. The project will also replace pavement in poor condition. 

Contact Information

Dave Bauman
Project Manager
636-949-3237

Current Project Activities

  • Truman Road will be restriped from Ehlmann Road to Point West Blvd. After the striping is complete, north and southbound traffic will be travelling on the current southbound lanes
  • Millstone Weber started to remove the existing pavement the week of March 25
  • The Sunbrook apartment entrance was poured the week of April 16th
  • The approach to Chemtron was complete the week of May 6th
  • Crews will begin paving operations on the northbound lanes of Truman the week of June 10th 


Project Timeline

truman ph 2 timeline

Project Progress

truman ph 2 progress

Project Budget

truman budget