West Sandfort & Truman Stormwater Improvements

Impacted Ward: 6

Contractor: JTL Landscaping


Project Description

The West Branch of Sandfort Creek Bank Stabilization project provides stabilization along both sides of the creek for approximately 1,000 linear feet to protect existing buildings and infrastructure. The project is located along the West Branch of Sandfort Creek at Truman Boulevard and Franks Drive.  The project limits are between the stormwater discharge ditch from the thirty six inch  pipe at Truman Terrace Subdivision and the existing nine foot by 10 foot box culvert at Truman Boulevard.

Project Location

Along the West Branch of Sandfort Creek at Truman Boulevard and Franks Drive
Project Map

Contact Information

Tim Rohrbacker
Project Manager
636-949-3237
Tim.Rohrbacker@stcharlescitymo.gov 

Project Activities

  • Project Charter approved November 2017.
  • Survey was complete in April 2018.
  • Preliminary plans were approved in June 2018.
  • Work on this project resumed August 23, 2019. The contractor began to clear and re-establish the creek from all of the rain damage. Also, the contractor started banking along the slopes to place rock to help stabilize the slope and rock toe.
  • Construction is expected to be completed March 2020.