Thrush & Mayer/Treadway Storm Sewer Improvements - 17STM25

Construction Wards - 9 & 10

Project Description

This project combines two Proposition P Projects: Thrush Drive Storm Sewers and Mayer/Treadway Storm Sewers. Property in Lake Forest receives overland flow from Thrush Drive. The overland flow floods the pool and pool house on a frequent basis. This project will construct stormwater improvements at the end of Thrush drive. The project will also address a deteriorated 36" CMP from Droste Road to the outfall at 819 Treadway Avenue.

Contact Information

Mark Rees
Project Manager
636-949-3237

Current Project Activities

  • Project Charter was approved in January 2018
  • A project design Open House is scheduled from 5:30p - 7p on December 5, 2018 in the Null Elementary gymnasium (435 Yale Blvd. St Charles, MO 63301)


Project Timeline

thrush timeline

Project Progress

thrush progress

Project Budget

thrush budget