Thrush & Mayer/Treadway Storm Sewer Improvements

Impacted Ward: 10


Project Description

This project combines two Proposition P Projects: Thrush Drive Storm Sewers & Mayer/Treadway Storm Sewers. Properties in Lake Forest, Hunters Ridge & Beacon Hill receive overland stormwater runoff from Thrush Drive & Principia Avenue. The overland flow causes localized flooding of a pool, pool house & backyards on a frequent basis. This project will construct stormwater improvements along Thrush Drive & Principia Avenue. The Mayer/Treadway stormwater improvements will address the deteriorated corrugated metal pipes along Treadway Avenue.

Project Location

Along Thrush Drive and Principia Avenue
Treadway Avenue and Mayer Drive
Project Map

Contact Information

David Bauman
Project Manager
636-949-3237
david.bauman@stcharlescitymo.gov 

Project Activities

  • Project Charter was approved in January 2018.
  • Engineering Staff held a project Open House on December 5 at Null Elementary.
  • Pavement Solutions finished grading and installing the creek bank slope protection throughout Treadway Avenue. Storm sewer improvements continue.  
  • May 2020 - the new storm sewer in Lake Forest is complete. Contractor has finished grading yards and installing the sod in Lake Forest. 