Cunningham & Woodlawn Drainage and Intersection Improvements

Impacted Ward: 2
Contractor: Aztec Construction Specialties, LLC.


Project Description

This project will remove existing curb and pavement and install seven new storm inlets along with approximately 205 linear feet of new pipe. Additionally, approximately 310 linear feet of new construction curb and gutter and 225 square yards of new asphalt pavement will be installed. 

Project Location

Intersection of Cunningham Avenue and Woodlawn Drive.
Project Map

Contact Information

Tim Rohrbacker
Project Manager
636-949-3237
tim.rohrbacker@stcharlescitymo.gov 

Project Activities

  • Construction began the week of February 24, 2020. 
  • Potholing and sawcutting the street will begin in order to locate underground utilities, and new storm structures and pipes will be installed starting the week of March 2, 2020. 
  • Possible closures of either Cunningham or Woodlawn can be expected. Detours will be set up.