Impacted Wards: 1
Design Consultant: TWM, Inc.
Project Description
Properties along Clark Street from Fifth Street to the Missouri River are subject to frequent flooding due to the undersized and sub-standard storm sewer system. This project is to replace undersized storm sewers along Clark Street from Fifth Street to the Missouri River outfall, and along Second Street from Clark Street to Lawrence Street. Additionally, the project is to replace the water mains along Clark Street from Fifth Street to Second Street as identified in the 2011 Water Master Plan. This project will incorporate recommendations from the Clark Street Complete Street Study.
Project Location
Along Clark Street from Fifth Street to the Missouri River outfall
Along 2nd Street from Clark Street to Lawrence Street.
Project Map
Contact Information
Anjana Kittu
Project Manager
636-949-3241
anjana.kittu@stcharlescitymo.gov
Project Activities
- Project Charter was approved May 2019
- Field investigations have been completed and preliminary design plans are currently under review.
- Plans for improvement along 2nd and Lawrence are underway.
- Construction expected to begin Spring 2021